Effects of Quality Control Practice on Performance of Building Construction Projects in Borama District, Somaliland

PDF Review History

Published: 2024-03-11

Page: 66-73


Abdifatah O. Nour *

Department of Construction Management, School of Postgraduate Studies and Research, Amoud University, Somaliland.

Werku Koshe Hareru

Department of Construction Management, School of Postgraduate Studies and Research, Amoud University, Somaliland.

*Author to whom correspondence should be addressed.


Abstract

The performance of building construction projects is highly affected by many factors. In Borama, 70% of construction projects does not meet the expected project cost, time, and scope. Therefore, this study aimed and investigated the effect of quality control practices on the performance of building construction projects in Borama District Somaliland. The study used a cross-sectional survey design with a sample of 92 workers in the 17 construction companies in the Borama district. The study uses a questionnaire as a data collection method. The result show that, there is no quality control standard/code in Somaliland due to these projects are adopting a foreign building code, but the foreign codes are not considering the Somaliland weather conditions, working environment and culture. And the study concluded that, current quality management (R = 0.568, p = 0.000 < a = 0.05), supervision of work (R = 0.671, p = 0.000 < a = 0.05), and construction quality (R = 0. 0.358, p = 0.001 < a - 0.05)   model show that a statistical significance on the performance of building construction projects in Borama district.  Secondly, the study found a significant positive correlation between quality control management on performance building construction projects construction companies. This shows that, if current quality management is practiced well, the performance of the building construction projects are improved.

Keywords: Current quality management, supervision of work, construction quality, project performance


How to Cite

Nour, A. O., & Hareru , W. K. (2024). Effects of Quality Control Practice on Performance of Building Construction Projects in Borama District, Somaliland. Asian Research Journal of Current Science, 6(1), 66–73. Retrieved from https://jofscience.com/index.php/ARJOCS/article/view/5

Downloads

Download data is not yet available.

References

Tan CK, Abdul-Rahman H. Preliminary research into overcoming implementation problems in construction projects. Proceeding of the 4th Micra; 2005.

Majewska, Ropel, Sustainable building material for green building construction, conservation and refurbishing sustainable building material for green building construction, Conservation and Refurbishing; 2011.

Frank Harris, Prof. Ronald McCaffer, Francis Edum-Fotwe (With). ISBN: 978-1-118-51018-6 February Wiley-Blackwell; 2013;576.

Crosby, Battikha MG. Quality management practices in highway construction’, Emerald. 1979;532-550

Wu Y, Huang Y, Zhang S, Zhang Y. Quality self-control and co-supervision mechanism of construction agents in the public investment project in China. Habitat International. 2012;36(4):471–480. Available:https://doi.org/10.1016/j.habitatint.2012.05.002

Chung HW. Understanding Quality Assurance in Construction a Practical Guide; 1999.

Olatunji A. Effect of Quality Management Practices Used on Construction Project Performance; 2010.

Vadivel TS. Analyzing the factors affecting quality in construction. It. 2016;4(33):1–6.

Ali AS, Wen KH. Workmanship. 2011; 2 (1):59–69.

Antunes R, Gonzalez V. A production model for construction: A Theoretical Framework.Buildings. 2015;5(1):209–228. Available:https://doi.org/10.3390/buildings5010209

Vadivel TS. Analyzing the factors affecting quality in construction. It. 2016;4(33):1–6.

Ali AS, Wen KH. Workmanship. 2011;2 (1):59–69.

Antunes R, Gonzalez V. A production model for construction: A Theoretical Framework. Buildings. 2015;5 (1):209–228. Available:https://doi.org/10.3390/buildings5010209

Biniyam A. Assessment of Quality Management Practices of Ethiopian Contractors Focused on Building Construction Projects. 2018;96.

Hughes M. Principles and practice of linear bearings; 1979.

Werku Koshe, Jha KN. Investigating causes of construction delay in ethiopian construction industries. Journal of Civil, Construction and Environmental Engineering. 2016;1(1):18-29.

DOI: 10.11648/j.jccee.20160101.13

Teshome HM, Gobana AB. A review of the quality management system. 2018;5(1): 444–447.

Juran JM. quality control handbook, McGraw-Hill Book Co., Inc. New York; 1988.

ISO 9000 for Contractors, E & FN Spon published in the Taylor & Francis e-library; 2002.